background image
22
i7 |
abraj kudai
lean concrete (yellow area in figure 3).
Only one tower was designed with a piled foundation (purple
area in figure 3). This was done to allow a safe transmittal of the
structural loads to the lower deep sound bedrock, for which the
replacement solution was judged to be uneconomical.
Designing the foundations: The evolution from a uniform
method to a discrete one
In the initial design of Abraj Kudai's foundation, we used a
uniform modulus of subgrade reaction k under each tower
(as shown in Figure 4). The mat area was divided into large zones,
for which a specific average k value was considered.
The resulting settlement of the founding ground (as shown
in Figure 5) appeared rough. Importantly, no significant
variability was identified between successive structural
columns/core elements.
Faced with the limitations of the first method, we changed
strategy. The discrete area method was applied to the
60,000 m
2
mat foundation of Abraj Kudai project.
The new k modulus presented a large variability across
the project's large mat foundation (see Figure 6).
The resulting k values accounted for the properties of
the founding rock, the anticipated structural loads and the
distribution of those loads across the foundation. As expected,
softer and more representative k values emerged for elements
in the center of the mat. They increased towards the mat edges,
with maximum values typically appearing at the mat corners.
Figure 7 illustrates the predicted settlement of the designed
foundation. The revised analysis clearly shows a gradually varying
settlement that increases with the intensity of the load in the
center and lessens at the extremities, as it should be in reality.
Figure 4
Figure 5
Learning points
The foundation design for Abraj Kudai was distinguished by
several good practices:
·
The accurate identification of the founding subgrade followed
by a 3D simulation of the site constraint, together, led to
selecting the appropriate foundation solution for each tower.
·
The structural and geotechnical engineers tightly coordinated
and collaborated on the discrete area method for the design of
the mat foundations.
·
The planned monitoring of the founding ground (bedrock)
and the structure's foundations will provide an actual ground
response, and will allow the structural and geotechnical
engineers to validate and calibrate their numerical models, and
consolidate their know-how in the area of study.
Figure 3