Location
Kazakhstan, Asia
Overview
JSC “Samruk-Energo” commissioned Dar to study the feasibility of a 2-MW peak Solar Photovoltaic power plant in the town of Kapchagay in Almaty Province, south-east of Kazakhstan.
We checked solar panel facilities, utilities, and infrastructure for a safe and efficient solar farm. We also prepared a master plan that covered the site’s general arrangement, general requirements of the solar PV power plant, civil requirements for building architecture, structural distribution, electromechanical services, and internal site roads.
We also ensured that the plant be built according to international and local codes and standards by coordinating with different suppliers and turnkey solution providers to assess each option or configuration for the plant.
Services
Markets